Mateusz Nowak | Noctiluca: What breaks when a synthetic and purification process scales 100 times, not 100 percent?
16:47 - 18:15
Other snippets from this talk
Summary of the clip:
What breaks when a synthetic and purification process scales 100 times, not 100 percent?
Certification is not just a technical gate. ISO certification and full supply-chain control bring consultant and accreditation costs that are often absent from the business plan. Investors may refuse to fund them because they add no value and do not improve the IP. The advice is to budget for that beforehand, because when the day arrives and that is the only item to finance, the money may not come.
The harder collision is timing. At the same moment as certification, the synthetic and purification process must scale 100 times—not 100 percent, 100 times. That challenge was reworked over nine months, six or seven times. The entire synthetic process and the entire supply chain were changed six or seven times in that nine-month period. It is not a straight line.
Each rework is not linear. You go back two steps before you can make another step forward. Two years ago, the material was thought to be mass-market ready: it worked and had nice device data. Yet the synthetic and purification scale-up still took this nine-month, six-or-seven-cycle effort. The working material and the scaled process are not the same milestone.
In this short video, you can learn:
* ISO certification and full supply-chain control introduce consultant and accreditation costs that investors may not fund because they do not improve the IP.
* Scaling the synthetic and purification process 100 times required six or seven changes to the entire process and supply chain over nine months.
* The material worked and had nice device data two years earlier, yet each scale-up step followed two steps back.
📋 **Clip Abstract** ISO certification and supply-chain control create consultant and accreditation costs that are often missing from the business plan and hard to fund later. Scaling the synthetic and purification process 100 times forced six or seven complete process and supply-chain changes over nine months, even though the material already worked and had nice device data.
About the speaker:
* Speaker: Mateusz Nowak
* Company: Noctiluca
* Event: Perovskite Connect 2026 | Berlin
* Location: Estrel, Berlin
Save the date: Perovskite Connect 2027 | 20 and 21 OCT 2027 | Berlin
Co-located with the Future of Electronics RESHAPED conference and exhibition
Learn more: https://www.techblick.com/perovskiteconnect
Intestered in exhibiting: learn more here: https://www.techblick.com/perovskiteconnect
#SyntheticProcessScaleUp, #PurificationProcessRework, #ISOCertificationCosts, #SupplyChainRework, #PerovskiteManufacturing, #MaterialsScaleUp
This is a highlight of the presentation:
Purity at Scale: High-Grade Materials for Reproducible Manufacturing, lessons from OLED for Perovskite
21 and 22 OCT 2026
Estrel, Berlin
Organised By:
More Highlights from the same talk.
03:30 - 05:06
How did OLED take 34 years and $100B capex to reach 25% of display market value?
How did OLED take 34 years and $100B capex to reach 25% of display market value?
The display business is measured in hundreds of billions of dollars, but only about half of that value is OLED today. OLED is beginning to dominate premium markets. The largest brands have invested roughly $100 billion over the last decade into that industry, into fabs and everything, showing the capex required in that industry.
The first OLED was invented in 1987. It took 34 years for the technology to mature to saturation in value, not in volume. Even today, volume is still with LCD. It reached 25% of the market after those 34 years. That timeline is a warning against assuming perovskite scaling will be fast; the speaker hears every two or three years that perovskite will be big within three to five years.
The OLED example also includes repeated hype and disillusionment curves—the same pattern the speaker says perovskites are going through. The key contrast is value saturation versus volume dominance: OLED reached 25% of market value while LCD still holds volume. For reproducible manufacturing, that distinction matters because capex, fab investment and market value can mature on a different schedule from unit volume.
In this short video, you can learn:
* OLED’s first invention was in 1987 and it took 34 years to reach 25% of market value.
* Even after that, LCD still held the volume while OLED dominated premium value.
* The largest brands invested about $100 billion over a decade into OLED fabs and infrastructure.
📋 **Clip Abstract** The display business is worth hundreds of billions of dollars, yet only about half its value is OLED. OLED took 34 years from its 1987 invention to reach 25% of market value despite roughly $100 billion of capex, with LCD still holding volume and perovskites facing the same hype cycles.
About the speaker:
* Speaker: Mateusz Nowak
* Company: Noctiluca
* Event: Perovskite Connect 2026 | Berlin
* Location: Estrel, Berlin
Save the date: Perovskite Connect 2027 | 20 and 21 OCT 2027 | Berlin
Co-located with the Future of Electronics RESHAPED conference and exhibition
Learn more: https://www.techblick.com/perovskiteconnect
Intestered in exhibiting: learn more here: https://www.techblick.com/perovskiteconnect
#OLEDMarketValue, #FabCapex, #PerovskiteHypeCycles, #ValueNotVolume, #PerovskiteSolarCells, #DisplayIndustry
19:53 - 21:21
What purity and process requirements will billion-dollar gigafabs impose on perovskite suppliers?
What purity and process requirements will billion-dollar gigafabs impose on perovskite suppliers?
Before anything else comes step T minus three: model the economics as they will work once the gigafab exists, not as they work today. The purity requirements and process requirements that will be in place have to be factored into the amount of cash needed to reach that point—an exercise the industry's current economics will not tell you.
A patent on the material in question was granted about two years ago and the product is still not in the market, because that entire process had to be worked through. Perovskite's early stage has tolerated imperfect samples—the sort that can be made in the back of a garage today—but that tolerance is a function of scale, not of the material.
Once a billion-dollar fab is running, imperfect samples stop being acceptable. A million agents will check every single box on that list, and their only job will be to catch the one parameter a supplier assumed it could get away with. There is no luck in that industry—only statistics.
In this short video, you can learn:
* Step T minus three is modelling the economics of a running gigafab, then pricing purity and process requirements into the cash required to get there.
* A material patented about two years ago is still not in the market because the surrounding process had to be completed first.
* Garage-grade perovskite samples pass today only because no billion-dollar fab is auditing every specification; at scale, verification is statistical, not lucky.
📋 **Clip Abstract** Scaling perovskite from garage samples to gigafab supply is framed as a purity and process problem before it is a materials problem: the economics of a billion-dollar line, not today's, set the specification. A patent held for two years and still unlaunched illustrates the cost of that path, and the argument closes bluntly—at gigafab scale a million agents check every box, so there is no luck, only statistics.
About the speaker:
* Speaker: Mateusz Nowak
* Company: Noctiluca
* Event: Perovskite Connect 2026 | Berlin
* Location: Estrel, Berlin
Save the date: Perovskite Connect 2027 | 20 and 21 OCT 2027 | Berlin
Co-located with the Future of Electronics RESHAPED conference and exhibition
Learn more: https://www.techblick.com/perovskiteconnect
Intestered in exhibiting: learn more here: https://www.techblick.com/perovskiteconnect
#GigafabPurity, #ProcessRequirements, #MaterialSpecification, #StatisticalVerification, #PerovskitePhotovoltaics, #SolarManufacturing
14:59 - 16:30
Why must perovskite material purity go from 99.9% to 99.99% for continuous production?
Why must perovskite material purity go from 99.9% to 99.99% for continuous production?
The first challenge is the last mile from 99.9% purity to 99.99%. Even if a customer does not require it, you will have to go higher because purity is the easiest thing for physicists and engineers to challenge. Otherwise, every weekly production problem can be blamed on the material, and you must prove it wrong.
The second challenge is that once that purity is achieved, the impurities must always be the same. A factory running for 10 days straight lets even the smallest impurities add up. 99% purity was okay when production or a demo took a couple of hours, but it is no longer okay for continuous operation.
For a production line continuously operating for two or three weeks, impurity accumulation changes the requirement. This is tied to scale-up: it is not only a matter of being okay with a partner, but of impurities accumulating as the line keeps running. Continuous manufacturing therefore demands both higher purity and consistent impurities.
In this short video, you can learn:
* Moving from 99.9% to 99.99% purity removes an easy target for production-failure blame.
* Impurities must stay identical because even the smallest amounts accumulate over 10 days of continuous factory operation.
* 99% purity suffices for hours-long demos but not for production lines running two or three weeks.
📋 **Clip Abstract** The clip frames purity as a last-mile challenge: 99.9% to 99.99% is needed even when customers do not demand it, because production problems otherwise get blamed on the material. It then shows why consistent impurities matter, since 99% purity suits short demos but not lines running 10 days or two to three weeks.
About the speaker:
* Speaker: Mateusz Nowak
* Company: Noctiluca
* Event: Perovskite Connect 2026 | Berlin
* Location: Estrel, Berlin
Save the date: Perovskite Connect 2027 | 20 and 21 OCT 2027 | Berlin
Co-located with the Future of Electronics RESHAPED conference and exhibition
Learn more: https://www.techblick.com/perovskiteconnect
Intestered in exhibiting: learn more here: https://www.techblick.com/perovskiteconnect
#PurityLastMile, #ImpurityAccumulation, #ContinuousProductionLine, #99Point99Purity, #PerovskitePV, #MaterialsManufacturing
About this talk
→ Purity at Scale: High-Grade Materials for Reproducible Manufacturing, lessons from OLED for Perovskite · Mateusz Nowak · Perovskite Connect 2026